UK Supreme Court returns to orthodox liquidated damages approach

The UK Supreme Court in its recent judgment in Triple Point Technology v PTT Public Company[1] has brought welcome clarity in relation to the drafting and interpretation of liquidated damages clauses[2] in construction, commercial and technology contracts. The judgment also deals with the relationship between liquidated damages clauses and caps on liability. We summarise the judgment and provide some key points for drafting liquidated damages clauses and related caps on liability.
Author(s): Melissa Perkin
A person is highlighting text on a printed contract document with a yellow marker. The document, which discusses the UK Supreme Court's return to an orthodox liquidated damages approach, is placed on a wooden desk next to a keyboard and mouse. Various sections and terms have some text already highlighted.

Background

Triple Point was engaged to design, implement and provide ongoing support and maintenance of a software system for PTT’s commodity trading and risk management. The contract provided for milestone payments on achievement of certain deliverables and damages for delay. It also provided a cap on Triple Point’s total liability to PTT under the contract, but stated that the liability cap did not apply to liability resulting from fraud, negligence, gross negligence or wilful misconduct. 

Work under the contract was significantly delayed. While PTT paid Triple Point’s initial invoice, PTT refused to pay later invoices on the basis that the dates for payment were tied to the milestones for completion. Triple Point did not dispute that it had not met the milestones but refused to continue with the works without payment. Triple Point suspended work. PTT gave notice that it was terminating the contract on the basis of wrongful suspension by Triple Point. Proceedings were brought by Triple Point against PTT for payment of the sums outstanding under its invoices. 

The issues on appeal to the Supreme Court were: 

  1. Whether liquidated damages were payable for work that was never completed or accepted by PTT? 
  2. Whether the exclusion of liability for “negligence” from the liability cap also include liability arising from a breach of a contractual duty of care? and
A person is typing on a laptop keyboard. The laptop screen displays lines of code in a text editor, perhaps analyzing a recent legal development like the UK Supreme Court returning to the orthodox liquidated damages approach. The person's left hand and wristwatch are visible. The background consists of a wooden surface.
  1. If PTT was entitled to liquidated damages, was this amount included in the liability cap? 

Issue 1 – Were liquidated damages payable where work was never completed? 

The accepted function of liquidated damages clauses was to benefit both the employer (who avoids having to prove actual loss flowing from delay) and the contractor (who has certainty as to its liability if delay occurs). 

The Supreme Court affirmed the general principle that liquidated damages accrue up to termination of a contract, irrespective of whether or not the works have been completed and accepted by the employer. Parties must be taken to know that the accrual of liquidated damages comes to an end when the contract is terminated. 

Following termination, however, the innocent party was entitled to seek general damages for the breach. The Supreme Court held that clear words would be required to overturn this “orthodox approach”.

Issue 2: Did damages for Triple Point’s negligent breach of contract fall within the exception to the liability cap for negligence? 

Courts will start from the assumption that in the absence of clear words, the parties did not intend their contract to derogate from the normal framework of rights and obligations established by the common law. This supported giving “negligence” its straightforward and ordinary legal meaning and to reinforce the general principle that clear words were needed to restrict valuable rights. The concept of negligence in the contract covered both tortious acts and breaches of a contractual requirement to exercise reasonable care and skill. 

Issue 3: Did liquidated damages fall within the liability cap? 

As liquidated damages were found to arise from negligence (ie, breach of contractual duty), they were therefore excluded from the liability cap. However, sums payable as liquidated damages should still have counted towards the exhaustion of Triple Point’s general cap that applied to the claim for wasted costs, other damages etc. 

Conclusion and comment?

The UK Supreme Court’s decision represents a welcome return to orthodoxy in the area of liquidated damages for delay. The judgment also provides a useful reminder of the correct way to analyse accrued contractual rights prior to termination, with a common theme running throughout: such accrued rights apply up to termination and can only evaporate if the parties have clearly and expressly agreed that this should be the case. 

Triple Point provides us with key points when drafting liquidated damages clauses: 

  • Liquidated damages clauses should be carefully and clearly drafted to specify their application, both up to and after termination of the contract; 
  • The relationship between liquidated damages clauses and any limitation of liability clauses should be clearly defined; 
  • Parties should consider if any liquidated damages that may be payable by the contractor are within or outside of the general liability cap; and 
  • Any carve-outs from the liability cap should be clearly identified. 

References

[1] Triple Point Technology, Inc (Respondent) v PTT Public Company Ltd (Appellant) [2021] UKSC 29.

[2] Liquidated damages clauses stipulate the amount of money payable as damages for loss caused by a breach of contract, irrespective of the actual loss suffered.

Other resources you might like

If you found this article helpful and are interested in learning more, there is a wealth of other resources available on our website. We have a wide array of articles and guides on a variety of topics, each designed to provide you with a deeper understanding of the subject matter. We encourage you to explore these resources and deepen your knowledge.

Grocery store produce section with shelves filled with fresh greens, including bags of lettuce and bunches of radishes. The vibrant green and red vegetables are neatly arranged in rows under bright lighting.

GICA and the Dispute Resolution Scheme in action

The first adjudication decision under the Grocery Industry Dispute Resolution Scheme (the Scheme) (www.grocerydispute.co.nz ) has been issued.
A red cable car is pictured traveling uphill in an urban area with a lush green field, city buildings, and mountains in the background. The scene is bright and clear under a blue sky, resembling the clarity often sought in discussions about reduction of damages for contributory negligence.

Leaky Home Case: Failure to obtain a building report results in reduction of damages for contributory negligence

Apportionment for contributory negligence allows a court to share the responsibility between parties in circumstances where the test for causation and remoteness of damage justifies it. It doesn’t mean a respondent will not be held liable for negligence, but it can affect the amount of damages awarded to a claimant, as Roberts v Jules Consultancy Limited (in liq) [2021] NZCA 303 has shown.
A woman with curly hair and glasses, dressed in a turquoise top, holds folders against her chest with one hand while resting her other arm on her forehead. She stands in front of a plain off-white wall, appearing tired or stressed.

Unfair terms in consumer contracts – important changes to the Fair Trading Act 1986

A 2018 Ministry of Business, Innovation & Employment (MBIE) survey of small businesses found that 45 per cent of participants considered that they had been offered unfair contract terms in the last year, and 47 per cent considered that they had otherwise been treated unfairly.[1]