The Court of Appeal sounds the all clear and it’s business as usual under the CCA: so file a payment schedule or pay up!

A decision issued by the High Court last year caused a “head in hands” moment in the construction industry in relation to the payment claim regime. The High Court set aside a statutory demand which had been filed to enforce a payment claim as a debt due even though no dispute had previously been raised by way of a valid payment schedule.[1] The Court of Appeal has now overturned that decision and confirmed that if a party to a construction contract wants to challenge a payment claim, they must issue a valid payment schedule.[2] Let’s look at what happened.
Author(s): Maria Cole
A construction worker wearing a yellow hard hat, safety glasses, and gloves leans on a wooden surface at a construction site. He is looking at the camera, and the background shows a wooden building under construction with windows and scaffolding.

Background

Demasol Ltd (Demasol) and South Pacific Industrial Ltd (South Pacific) entered into a construction contract for Demasol to carry out works at an old gas facility. The works involved demolition of a large bin tank which contained asbestos. The quoted price for the works was $100,000.00 but excluded the asbestos we cannot see. The works were carried out but took longer than the parties expected. Demasol claimed the scope of the works had increased during the course of the contract. It sought payment for the additional works, claiming them as variations to the contract. It served two payment claims between January and March 2021, totalling just over $390,000.00.

On receipt of service, South Pacific did not pay the claimed amounts, or issue payment schedules under the CCA indicating it disputed the claimed amounts. Instead, in April 2021 it wrote to Demasol advising it rejected all but one of the seven variations in payment claim 2 and asserted it had its own claims against Demasol for non-performance.

There was to-ing and fro-ing between the parties and the end result was that in May 2021, Demasol served a statutory demand on South Pacific for just under $305,000.00.

South Pacific responded by filing an application in the High Court, seeking to set aside the statutory demand on the basis the payment claims were invalid. By the time the matter came before the High Court, payment claim 1 had been paid in full.

A close-up view of a rusted industrial structure against a clear blue sky. The structure features interconnected pipes, metal platforms, and ladders, giving it a complex and towering appearance.

A rabbit hole moment...

The Associate Judge was persuaded by South Pacific to look into the merits of its defence, being that the payment claims issued by Demasol were not valid under the terms of the contract. After looking into the substance of both payment claims, the Associate Judge found that it was reasonably arguable that payment claim 2 was not valid because much of the amount claimed related to variations that were arguably not authorised. The Associate Judge then found that in any event, it was reasonably arguable that both payments claims were invalid on the basis that they were not issued in accordance with an expressly agreed term which provided for a single payment on completion. 

On that basis, the Associate Judge set aside Demasol’s statutory demand. 

Demasol appealed. 

A judge's hand holding a wooden gavel over a round wooden sound block on a dark wooden table. The image is closely cropped to focus on the gavel and block, with a blurred background indicating an ICSID awards courtroom setting.

The Court of Appeal to the rescue!

Fortunately, the Court of Appeal was having none of it. It was unanimous in finding that the Associate Judge was in error when she looked into the terms of the contract to decide whether Demasol was entitled to serve payment claim 2.[3]  

The Court of Appeal said: 

[41] The Associate Judge sought to consider the contract between Demasol and SPI to determine whether Demasol was entitled to serve the claim. In our view, she erred in undertaking this enquiry. Section 20(1) of the CCA deals with when a payee may serve a payment claim. If the construction contract provides for the matter, a payment claim can be served at the end of the period specified in or determined in accordance with the contract. If the contract does not provide for the matter, in the case of a progress payment, a payment claim can be served at the end of the relevant period referred to in s 17(2) — that is, the period commencing on the day of the month on which the construction work was first carried out and ending on the last day of that month, and each month thereafter. In the case of a single payment expressly agreed under s 14(1)(a), if the contract does not provide for the matter then a payment claim can be served following the completion of all of the construction work to which the contract relates. 

A woman with shoulder-length dark hair and glasses is seated on a couch, reviewing several sheets of paper. She is wearing a beige sweater and light-colored pants. There are modern light fixtures and a window with sheer curtains in the background.

[42] There was considerable debate before the Associate Judge as to which of these various provisions applied. We are not persuaded that it makes any difference for present purposes. If SPI wished to contend that Demasol was not entitled to serve a payment claim on it when Demasol did so, that was a point it could and should have taken by way of response in a payment schedule. However, SPI failed to file a payment schedule, and instead sought to raise the issue, along with others, only when Demasol took steps to enforce the debt in reliance on s 23(2)(a) of the CCA. 

Once it had reached this conclusion, the Court proceeded to look at payment claim 2. It found the claim met each of the statutory requirements under section 20 of the CCA for a valid payment claim. It noted that a payer becomes liable to pay the claimed amount if they do not serve a payment schedule on the payee within the time limit specified in the CCA. 

South Pacific became liable to pay the claimed amount when it failed to provide a payment schedule by the due date.  Demasol was therefore entitled to recover the unpaid portion of the claimed amount as a debt due in any court, plus costs. 

In closing, the Court of Appeal stated that South Pacific was not shut out from the CCA’s adjudication processes or from other proceedings. It could prosecute the various disputes it had put in issue notwithstanding payment to Demasol. It simply had to pay now and argue later.[4]

Conclusion

The purpose of the CCA is to keep cash flowing and the Court of Appeal has reconfirmed that loud and clear. If a party to a construction contract is served with a payment claim which it wants to dispute, it has to follow the procedures set out in the CCA. It must provide a payment schedule that sets out what it will pay, what it won’t pay, and explain why. It then needs to pay what it agrees is owing. If the claimant wants to argue the toss, it can head off to adjudication to settle things on the merits of its claim. 

References

[1] South Pacific Industrlal Ltd v Demasol Ltd [2021] NZHC 3597.

[2] Demasol Ltd v South Pacific Industrial Ltd [2022] NZCA 480.

[3] The Court of Appeal only considered payment claim 2, as payment claim 1 had been paid in full.

[4] Para [57].

Other resources you might like

If you found this article helpful and are interested in learning more, there is a wealth of other resources available on our website. We have a wide array of articles and guides on a variety of topics, each designed to provide you with a deeper understanding of the subject matter. We encourage you to explore these resources and deepen your knowledge.

Sense and violence: English courts reject offshore construction contractor’s $25 million indemnity insurance claim because its interpretation of the policy made no commercial sense and did violence to the language

In Technip v MedGulf, the English High Court and Court of Appeal dismissed a construction contractor’s $25 million (USD) indemnity insurance claim for damage it caused when it crashed into the project developer’s property during construction works in an offshore oil field. Both courts preferred the insurer’s interpretation of the policy’s ambiguously worded exclusion clause, finding the policyholder’s interpretation made no commercial sense and did far more violence to the natural meaning of the words.
A construction worker wearing a white safety helmet and a face mask is examining a floor plan attached to a concrete wall. The worker points at the blueprint with one hand while adjusting it with the other, standing in a partially constructed building, likely reviewing details related to the construction contract.

An adjudicator’s decision on a construction contract is definitely worth the paper it’s written on!

It’s only in rare circumstances that the courts will interfere with the decision of an adjudicator on a construction contract. A recent decision out of the English Technology and Construction Court (TCC) considered arguments that an adjudicator acted in breach of the principles of natural justice by reaching a decision on a basis not advanced by either party to the adjudication and by failing to consider a defence raised by the defendant.
A man wearing an orange hard hat and a white shirt with a black tie points to a large screen displaying architectural plans. He is standing in a modern office space, explaining the details of the design.

Southern Summary Judgment Stoush

In the Invercargill High Court, in Northlake Investments Limited v Civil Construction Limited [2023] NZHC 2715, a developer and contractor battled in substantive proceedings following an adjudication under the Construction Contracts Act 2002 (the Act). The key issue was whether an adjudicator’s determination on a disputed payment claim was not binding because the contractor had not complied with the contractual procedures for referral to adjudication, or whether the Act overrode those contractual procedures.

Get in touch

Contact our team today to see how we can help

Contact us

This field is for validation purposes and should be left unchanged.