Pandemics, lockdowns and contracts – can overseas courts give us any insight?

When the COVID-19 pandemic first arrived in New Zealand, there was widespread discussion amongst the legal community about the impact the pandemic and the Government “lockdowns” might have on contracts.[1] Two main avenues for obtaining contractual relief were explored: the doctrine of frustration, and force majeure clauses.

With the recent move into a Level 4 lockdown, it’s timely for us to revisit our thinking on this. Have the courts been able to fill in some of the gaps we had in our understanding of how COVID-19 might affect contracts? Interestingly, there has been little comment from the courts on these matters – perhaps parties have reached settlement, or perhaps the disputes are still making their way through the backlogged courts. However, we do have two cases to consider: one from Ireland, and one from Wales.
Author(s): Belinda Green
A person wearing a face mask is sitting in a dark room, illuminated by their laptop screen. Their hands are typing on the keyboard, perhaps drafting contracts or seeking insight from overseas courts during the pandemics lockdowns.

How the COVID-19 pandemic might affect contracts

When COVID-19 arrived in New Zealand in 2020, we wondered whether the doctrine of frustration or a force majeure clause might help release a party from a no-longer profitable contact.  The overall conclusion was that the standard for both was “very high”, and that it would depend on the particular circumstances of each contract (the usual refrain from legal commentators – although that doesn’t make it any less true!). A brief recap on the thinking is in order, before we move on to the cases for discussion.    

Doctrine of frustration

The doctrine of frustration applies to release a party from their contractual obligations if circumstances exist that mean the performance of their obligations is impossible due to no fault of their own.  The doctrine exists in law, so the parties can use it whether or not their contract mentions frustration.  

A woman wearing a mask is sitting at a desk, participating in a video call on her laptop during one of many pandemics lockdowns. The person on the screen is also masked. The desk features potted plants, a notebook, and small decor items, all set in a brightly lit room.

In general, the standard for showing that a contract has been frustrated is very high. The courts look for some kind of event that makes it impossible for the parties to perform the contract, and impossible to perform it for a reasonable length of time.  That makes it difficult to work out if it could apply in the COVID-19 scenario.  The contract might become less profitable (for example, due to a decrease in trade), but could still be performed.  The NZ Level 4 “lockdown” did perhaps make it impossible for some contracts to be performed, but was the duration of this lockdown long enough to have triggered the doctrine of frustration? It seemed unlikely, in most cases. 

Force majeure

Most of us will be familiar with force majeure clauses, although we may recognise them by the phrase “act of God” rather than the French term. These clauses allow a party to cancel or suspend the contract if a “force majeure” event occurs.  They wax and wane in popularity, but many commercial contracts contain such a clause. 

The contract will usually set out what kinds of events will be considered “force majeure”.  They are usually described as some kind of event beyond the control of the parties, and can sometimes look like a laundry list of events that might be more at home in an insurance contract (natural disasters, political unrest, etc). Because parties can agree their own wording, it was speculated that it could be easier to show that there has been a force majeure event rather than relying on the doctrine of frustration.  But “easier” is a relative term.  It was still hard to know if the COVID-19 pandemic or the lockdowns could be grounds for exercising a force majeure clause.   

Frustration in the Irish courts

In Issue 27 of ReSolution, we reported on Oyster Shuckers Limited T/A KLAW (1) v Architecture Manufacture Support (EU) Limited and Wooi Heong Tan [2020] IEHC 527, in which the Irish courts tested the argument of whether COVID-19 can be seen as a frustrating event allowing for the suspension of rent under the commercial lease. 

People are gathered on a city street for a parade. A person holds up a large Irish flag, which is prominently displayed. There is a traffic light and a street sign saying "Jackson Blvd" on the corner of a building in the background, reminiscent of times before pandemics lockdowns transformed public celebrations.

Force majeure in the E&W courts

More recently, the courts in England and Wales have tested the argument of whether COVID-19 can be seen as a force majeure event allowing for the suspension of contractual terms (Dwyer (UK) Franchising Limited v Fredbar Limited [2021] EWHC 1218 (Ch)).  

Dwyer and Mr Bartlett (acting through his company, Fredbar Limited) were parties to a franchise agreement, allowing Mr Bartlett to operate as a “Drain Doctor” in the Cardiff area. The Court provided a decision on a wide range of matters, including some comparatively brief commentary on the force majeure clause.  That clause suspended the agreement during any period the parties were prevented from complying with their contractual obligations because of an event designated by Dwyer to be a force majeure event.   

In March 2020, Mr Bartlett contacted Dwyer, asking it to designate the pandemic as a force majeure event.  The initial reason for this request was the downturn in work.  Dwyer refused to designate, saying that fewer jobs did not mean “force majeure”. Mr Bartlett repeated his request, noting that NHS Wales had advised him and his family to self-isolate for 12 weeks because his son was vulnerable to COVID-19. Dwyer refused to designate, again referring to turnover. 

The image shows the Union Jack flag of the United Kingdom flying on a flagpole with a gold finial against a cloudy sky background. Amidst pandemics, lockdowns, and legal complexities, the flag waves in the wind, displaying its red, white, and blue colors prominently.

The Court noted that the clause in the franchise agreement gave Dwyer the power to designate a force majeure event.  The UK Supreme Court had previously held that any one-sided discretion like this must be exercised honestly, in good faith, and genuinely.[2] By failing to properly consider the son’s health and the need to self-isolate, Dwyer had failed to exercise its discretion appropriately.   This ultimately did nothing to assist Mr Bartlett – Dwyer had repudiated the contract, but then offered a comprise that Mr Bartlett accepted. This meant that the contract remained on foot, despite the fact that a force majeure event ought to have suspended the provisions. 

The New Zealand context

There has been little commentary from the New Zealand courts – a handful of employment law cases, and a other few mentions of COVID-19 and frustration or force majeure appear in the court records – although more in the contractual manoeuvrings of parties in the leadup to litigation, than in the court findings themselves.  So, can we learn anything from these overseas cases?  

The Irish case was not a strong test case: it would be unusual for a court to find that only a particular clause of a contract had been frustrated.  And to argue for the suspension of rent because of frustration in the face of an express rent suspension clause was a hard sell.   

But what of Dwyer and Mr Bartlett? The arguments here were more robust, and indeed Mr Bartlett would have been successful were it not for subsequent actions overtaking the situation.  However, we also face some issues in trying to apply this case more broadly.  For example, the need for Dwyer to designate a force majeure event played a key role in the Court’s analysis.  This designation power is not the norm.  It would be more common for a force majeure clause to simply state the types of events that are force majeure 

A large steel bridge spans a deep blue body of water on a bright, sunny day. The skyline of a city with tall skyscrapers and a prominent tower is visible in the background under a clear blue sky with some scattered clouds, reminiscent of bustling days before pandemics reshaped our routines.

It’s also hard to compare Mr Bartlett’s circumstances in Wales with those in New Zealand – Mr Bartlett received a letter from the NHS recommending he self-isolate due to the health of his son; the New Zealand Government has issued country-wide and region-specific notices mandating that people stay at home.  Would Mr Bartlett’s scenario be similar to that of an “essential worker” who could have worked but was required to stay at home due to the need for another household member to self-isolate?  Perhaps.  It’s also not clear what impact the availability of other support was considered relevant – in Mr Bartlett’s case, the Court noted that Mr Bartlett was not entitled to government support (unlike Dwyer’s own employees had been), and that his financial position was such that the family house was on the line. Would the New Zealand Government’s relief packages cast a different light on how these events would have been viewed? 

All told, these cases don’t do much to advance our understanding of how the New Zealand courts might view the effect of the pandemic on contracts.  The refrain therefore remains the same:  the standard is “very high”, and whether or not a contract has been frustrated or a force majeure event has occurred will depend on the particular circumstances of each contract. 

References

[1] See for example these articles from DLA Piper and Minter Ellison for a flavour of what the large commercial law firms were talking about.

[2] Braganza v BP Shipping Limited [2015] UKSC 17.

Other resources you might like

If you found this article helpful and are interested in learning more, there is a wealth of other resources available on our website. We have a wide array of articles and guides on a variety of topics, each designed to provide you with a deeper understanding of the subject matter. We encourage you to explore these resources and deepen your knowledge.

A person is highlighting text on a printed contract document with a yellow marker. The document, which discusses the UK Supreme Court's return to an orthodox liquidated damages approach, is placed on a wooden desk next to a keyboard and mouse. Various sections and terms have some text already highlighted.

UK Supreme Court returns to orthodox liquidated damages approach

The UK Supreme Court in its recent judgment in Triple Point Technology v PTT Public Company[1] has brought welcome clarity in relation to the drafting and interpretation of liquidated damages clauses[2] in construction, commercial and technology contracts. The judgment also deals with the relationship between liquidated damages clauses and caps on liability. We summarise the judgment and provide some key points for drafting liquidated damages clauses and related caps on liability.

.nz Dispute Resolution Scheme – Annual Report release 

Australian Hague Rules: party to shipping dispute rails against arbitration clause

In Carmichael Rail Network Pty Ltd v BBC Chartering Carriers GmbH & Co KG, [1] the High Court of Australia assessed whether engagement in arbitration in a foreign jurisdiction could contravene law designed to protect cargo owners. The decision is an illustration of the stability of arbitration as a method of dispute resolution.

Get in touch

Contact our team today to see how we can help

Contact us

This field is for validation purposes and should be left unchanged.