Hong Kong Court of First Instance weighs up status of interim injunction. Was it an award?

Author(s): Alexander Lyall

In W v Contractor [2024] HKCFI 1452, an employer in a construction contract sought to appeal a decision made in arbitration regarding a call on a bond. In that decision, the arbitrator had made an interim injunction preventing the employer from calling on a bond for payment. The appeal rested on whether an interim injunction could be considered an award before a point of law could be examined.

The employer appealed the arbitrator’s decision on the grounds that the arbitrator had erred in law. Under section 6(4) of Schedule 2 of the Arbitration Ordinance, an appeal on law can only succeed if it was obviously wrong or the question is of general importance and the decision is open to serious doubt.

The Court noted that the threshold necessary to meet the standard of obviously wrong or open to serious doubt was high. As the first stage of the appeal is an application for leave, the Court is to look primarily at the arbitrator’s award and will limit the submissions by the parties. The Court applied the findings of an earlier judgment:

What has to be demonstrated to the Court, quickly and easily, without meticulous legal argument, is that the decision of the tribunal simply cannot be right, or that there are serious doubts as to the correctness or reasoning of the Award.

However, before considering whether the applied law met this standard, the Court directed that the fundamental status of the decision be examined. This is because, under section 6 of the Schedule, the Court is only able to consider an appeal on an arbitrator’s decision if that decision was an award. The question is, does this include interim injunctions? The Court referred to G v N [2024] HKCFI 721 to demonstrate the position that it did not.

The employer noted that in G v N, the decision was labelled as an interim injunction. In this case, the decision was called “an award”. However, the Court reiterated that it was concerned with the substance of the decision.

After assessing the decision’s nature, substance and form, the Court held that despite its name, the arbitrator’s decision was not an award. The Court noted that the injunction granted in the decision was interim in nature and was pending the conclusion of the resolution of the substantive dispute in the arbitration. The Court, therefore, found in favour of the contractor.

Other resources you might like

If you found this article helpful and are interested in learning more, there is a wealth of other resources available on our website. We have a wide array of articles and guides on a variety of topics, each designed to provide you with a deeper understanding of the subject matter. We encourage you to explore these resources and deepen your knowledge.

“Anchored to the contract” – UK Supreme Court concludes the MUR Shipping saga on force majeure and reasonable endeavours

The UK Supreme Court has overturned the judgment of the Court of Appeal in MUR Shipping, and held that a reasonable endeavours proviso in a force majeure clause does not require a party to accept an offer of non-contractual performance. In a unanimous decision, the Supreme Court focused on the importance of commercial certainty and that what is required by reasonable endeavours must be anchored to the contract.
The image shows the exterior of the Centre Pompidou in Paris, characterized by its high-tech architectural style. Prominent features include external escalators encased in transparent tubes and exposed structural elements in a lattice pattern.

Gas dispute to be aired in arbitration

Hong Kong Court refuses to set aside arbitral award over claim lawyer couldn’t read witness’ body language in virtual hearing The Supreme Court of Western Australia in Power and Water Corporation v Eni Australia B V [2022] WASC 376 considered whether a party to a gas supply agreement was justified in attempting to avoid an arbitration clause. On the facts, the application (based on an exception to the arbitration clause) for urgent declaratory relief was not met. Arbitration had to proceed as provided for in the contract.
A person wearing a helmet and polo attire from one of the prestigious polo clubs is riding a galloping horse on a grassy field, aiming a polo mallet at an airborne ball. Dense trees are visible in the background.

Lifestyles of the rich and famous: Polo clubs and (non) party parties

A company that acquired the Beverly Hills Polo Club trade mark was found by the English Court of Appeal to be bound by an arbitration clause in an agreement entered into by its predecessor owner of the trade mark.[1] The appeal involved issues of conflict of laws in relation to arbitration agreements and the assignment of trade marks.

Get in touch

Contact our team today to see how we can help

Contact us

This field is for validation purposes and should be left unchanged.