UK Supreme Court returns to orthodox liquidated damages approach

The UK Supreme Court in its recent judgment in Triple Point Technology v PTT Public Company[1] has brought welcome clarity in relation to the drafting and interpretation of liquidated damages clauses[2] in construction, commercial and technology contracts. The judgment also deals with the relationship between liquidated damages clauses and caps on liability. We summarise the judgment and provide some key points for drafting liquidated damages clauses and related caps on liability.
Author(s): Melissa Perkin
A person is highlighting text on a printed contract document with a yellow marker. The document, which discusses the UK Supreme Court's return to an orthodox liquidated damages approach, is placed on a wooden desk next to a keyboard and mouse. Various sections and terms have some text already highlighted.

Background

Triple Point was engaged to design, implement and provide ongoing support and maintenance of a software system for PTT’s commodity trading and risk management. The contract provided for milestone payments on achievement of certain deliverables and damages for delay. It also provided a cap on Triple Point’s total liability to PTT under the contract, but stated that the liability cap did not apply to liability resulting from fraud, negligence, gross negligence or wilful misconduct. 

Work under the contract was significantly delayed. While PTT paid Triple Point’s initial invoice, PTT refused to pay later invoices on the basis that the dates for payment were tied to the milestones for completion. Triple Point did not dispute that it had not met the milestones but refused to continue with the works without payment. Triple Point suspended work. PTT gave notice that it was terminating the contract on the basis of wrongful suspension by Triple Point. Proceedings were brought by Triple Point against PTT for payment of the sums outstanding under its invoices. 

The issues on appeal to the Supreme Court were: 

  1. Whether liquidated damages were payable for work that was never completed or accepted by PTT? 
  2. Whether the exclusion of liability for “negligence” from the liability cap also include liability arising from a breach of a contractual duty of care? and
A person is typing on a laptop keyboard. The laptop screen displays lines of code in a text editor, perhaps analyzing a recent legal development like the UK Supreme Court returning to the orthodox liquidated damages approach. The person's left hand and wristwatch are visible. The background consists of a wooden surface.
  1. If PTT was entitled to liquidated damages, was this amount included in the liability cap? 

Issue 1 – Were liquidated damages payable where work was never completed? 

The accepted function of liquidated damages clauses was to benefit both the employer (who avoids having to prove actual loss flowing from delay) and the contractor (who has certainty as to its liability if delay occurs). 

The Supreme Court affirmed the general principle that liquidated damages accrue up to termination of a contract, irrespective of whether or not the works have been completed and accepted by the employer. Parties must be taken to know that the accrual of liquidated damages comes to an end when the contract is terminated. 

Following termination, however, the innocent party was entitled to seek general damages for the breach. The Supreme Court held that clear words would be required to overturn this “orthodox approach”.

Issue 2: Did damages for Triple Point’s negligent breach of contract fall within the exception to the liability cap for negligence? 

Courts will start from the assumption that in the absence of clear words, the parties did not intend their contract to derogate from the normal framework of rights and obligations established by the common law. This supported giving “negligence” its straightforward and ordinary legal meaning and to reinforce the general principle that clear words were needed to restrict valuable rights. The concept of negligence in the contract covered both tortious acts and breaches of a contractual requirement to exercise reasonable care and skill. 

Issue 3: Did liquidated damages fall within the liability cap? 

As liquidated damages were found to arise from negligence (ie, breach of contractual duty), they were therefore excluded from the liability cap. However, sums payable as liquidated damages should still have counted towards the exhaustion of Triple Point’s general cap that applied to the claim for wasted costs, other damages etc. 

Conclusion and comment?

The UK Supreme Court’s decision represents a welcome return to orthodoxy in the area of liquidated damages for delay. The judgment also provides a useful reminder of the correct way to analyse accrued contractual rights prior to termination, with a common theme running throughout: such accrued rights apply up to termination and can only evaporate if the parties have clearly and expressly agreed that this should be the case. 

Triple Point provides us with key points when drafting liquidated damages clauses: 

  • Liquidated damages clauses should be carefully and clearly drafted to specify their application, both up to and after termination of the contract; 
  • The relationship between liquidated damages clauses and any limitation of liability clauses should be clearly defined; 
  • Parties should consider if any liquidated damages that may be payable by the contractor are within or outside of the general liability cap; and 
  • Any carve-outs from the liability cap should be clearly identified. 

References

[1] Triple Point Technology, Inc (Respondent) v PTT Public Company Ltd (Appellant) [2021] UKSC 29.

[2] Liquidated damages clauses stipulate the amount of money payable as damages for loss caused by a breach of contract, irrespective of the actual loss suffered.

Other resources you might like

If you found this article helpful and are interested in learning more, there is a wealth of other resources available on our website. We have a wide array of articles and guides on a variety of topics, each designed to provide you with a deeper understanding of the subject matter. We encourage you to explore these resources and deepen your knowledge.

A person wearing a face mask is sitting in a dark room, illuminated by their laptop screen. Their hands are typing on the keyboard, perhaps drafting contracts or seeking insight from overseas courts during the pandemics lockdowns.

Pandemics, lockdowns and contracts – can overseas courts give us any insight?

When the COVID-19 pandemic first arrived in New Zealand, there was widespread discussion amongst the legal community about the impact the pandemic and the Government “lockdowns” might have on contracts.[1] Two main avenues for obtaining contractual relief were explored: the doctrine of frustration, and force majeure clauses.

With the recent move into a Level 4 lockdown, it’s timely for us to revisit our thinking on this. Have the courts been able to fill in some of the gaps we had in our understanding of how COVID-19 might affect contracts? Interestingly, there has been little comment from the courts on these matters – perhaps parties have reached settlement, or perhaps the disputes are still making their way through the backlogged courts. However, we do have two cases to consider: one from Ireland, and one from Wales.

.nz Dispute Resolution Scheme – Annual Report release 

A woman sits at a desk in a modern office, holding and examining papers. She is dressed in professional attire, with a laptop, notepad, and documents spread out in front of her. Amidst the shelves, plants, and framed certificates, she scrutinizes contract clauses for wilful breaches.

Wilful Breaches of Contract – Do Exclusion Clauses and Liability Caps Still Work?

Can deliberate or wilful contract breaches still benefit from clauses that limit or exclude liability? The English High Court recently considered this issue in Mott Macdonald Ltd v Trant Engineering Ltd,[1] which confirmed that clauses limiting or excluding liability for claims will be given effect on their plain and ordinary meaning. If any limitation or exclusion is not intended to apply to a deliberate or wilful action, clear wording to that effect is required.

Get in touch

Contact our team today to see how we can help

Contact us

This field is for validation purposes and should be left unchanged.